Project 147 – Great Divide & Black Eagle

The Project

Located outside of Helena And Great Falls, Montana

  • 2 Utility-Scale, Ground-Mount Solar Plants ( Great Divide & Black Eagle)
  • Both Project Sizes: 4.3 MW
  • Modules Per Project: 12,960
  • Rows Per Project: 240
  • Tracker: Solar FlexRack TDP Tracker

Project Level : Difficult

Limited Regional Resources:

  • Skilled Labor
  • Installation Equipment
  • Daily Supplies
  • Cell Phone Coverage

Rocky Soil Conditions:

  • Induced Element of Unpredictability
  • High Refusal Rate On Both Great Divide & Black Eagle with Site Specific Soil Issues
  • Sloping Terrain on Black Eagle
12155

Hours of Work

June 2017

Construction Date

4.3 each

Size[MW]

Montana

Location

Solutions

Method’s applied to deal with challenges:

  • Solar FlexRack’s On-site Team and Rapid Response Rate
  • Engineering Knowledge and Expertise Deliver Economical Solutions
  • Refusal Multi-Option Solution Creates Flexibility and Cost Savings
  • Preferred Installers: Customer-Centric with Approved Methods & Accurate Data
  • Experienced Installer with fast communication process to implement changes!

Costumer Benefits

500 Posts Refusals in Rocky Soil

Solar FlexRack’s Rapid Response system and the expert engineering analysis  delivered a fast, and thorough response to the encountered challenges. Given the great teamwork and the cost effective cut&drill solution we were able to complete the job on time with no deviation from the original schedule. The robust, reliable racking & tracking system combined with the highly-qualified field presence reduces the response time and leads to a successful project execution.