Foundation challenge
Foundations in a rock quarry are challenging – you can see that we had our hands full to mitigate the issue – especially given the tremendous precipitation during the first quarter in 2017.
On our way
This Nextracker install had some challenges but we were able to work through them and complete the project within the given time frame. Visit : Nextracker
Hours of Work
Construction Date
Size[MW]
Location
A Team – in Good & Bad
Not only is this couple married – no they are also partners in crime – meaning they install solar systems around the country! They have the knowledge and dedication to make every project right – Thank you both for working through mud and rain!
Project Numbers
A sea of 4,354 solar panels installed at a former rock quarry just outside northwest Novato is expected to begin powering 300 homes in 30 days. The project stands at 6.5 feet tall on 11.5 acres of the 952-acre quarry where serpentine rock was once mined. To see more:
