Project 70 – Fresno Cogen Solar Project

Construction

Synchronized pile driving is not Olympic, but we had a tight schedule as the system needed to be done at a certain day in April, so we pushed it! The soil conditions were not favorable so we had to deal with refusals, but it all worked out.

Tracker

Trackers are taking over the market. Here we installed a Clavijo tracker with the central drive shaft.

11711

Hours of Work

April 2015

Construction Date

3.4

Size [MW]

Fresno , CA

Location

Team

It is such a difference when you have the right team together – it’s much more fun and things are getting done. The quality is right and the client is happy – great job!

Ribbon Cutting

Finally done – it was a great pleasure working together.

Thank you for this great project!

Hear more from our client: Client testimonial 04 |SAT