High-Load Ground Screw Foundation Integration
Rather than standard driven piles, the True Organic site utilized 436 APA ground screw anchors engineered to achieve a 6′ 7″ embedment depth. Ground screws deliver optimal uplift resistance and long-term structural integrity in native Central Valley soil types, eliminating the need for pre-drilling while meeting rigid design loading thresholds.
Integrating Nextracker XTR with APA A-Frame foundations across 24 tables required precise torque tube alignment, riser leveling, and slew drive placement. Sunstall’s team performed strict quality control on all bomb tails, BHAs, and dampeners—verifying 109 ft-lbs torque specs for M12 hardware.
1,107
Hours of Work
Aug 2026
Construction Date
0.825
Size[MW]
Helm, CA
Location
Proactive Technical Problem-Solving
Field conditions often demand rapid technical resolutions. During execution, Sunstall collaborated directly with project engineers and suppliers to streamline racking hardware requirements—verifying torque requirements for M12 dampener connections, resolving edge-clamp mounting specifications, and completing custom frame modifications—ensuring project flow was maintained without sacrificing structural compliance or manufacturer warranties.
100% Completion: Key Takeaways for Solar Asset Owners & EPCs
- Desktop Estimates Must Match Field Realities: Validating site conditions early ensures foundation choices (like ground screws vs. driven piles) perform reliably over a 25+ year operational lifespan.
- Hybrid Racking Expertise Matters: Combining tracker systems from one vendor with foundation mounts from another requires an installation team thoroughly versed in technical bulletins and multi-vendor coordination.
- Turnkey Reliability: From initial mobilization to commissioning, experienced field management protects asset owners from long-term liability while keeping project schedules on track.